Penderwood Water Storage Tank

Public Meeting
A public meeting was held on April 11, 2007 to discuss a 3-Phase project beginning with the addition of a 5.5-million gallon water storage tank to the Fairfax Water system.

Materials presented at the meeting are available for viewing here. These materials are in Adobe PDF format. Please note that some files are large, more than 1 mb, and may take sometime to download.

Q&A Public Information Meeting (April 11, 2007)
General Site Layout
Project Graphics
Original Special Exception Plat (1977)

Meeting flyer (April 11, 2007)

To ensure a safe, continuous and reliable drinking water supply, Fairfax Water must increase the amount of water stored in the distribution system. Construction of the proposed Phase 1 storage tank is part of a multi-million dollar investment being made by Fairfax Water to increase system reliability. The system reliability improvements project will also add standby power generation at several major water production and pumping facilities.

With a capacity of 5.5-million gallons, this new water storage tank will be located adjacent to the existing elevated storage tank on West Ox Road in the Penderwood area.

Storage tank construction is estimated to take approximately 18-months. Construction activity will be restricted to normal working hours. The impact to traffic flow on West Ox Road is expected to be minimal. Every effort will be made to minimize dust, silt and environmental impacts during construction. All applicable County construction requirements will be satisfied during this work. Disturbed unpaved areas will receive new plantings or be seeded with grass upon completion of the storage tank installation.
 

Artist’s Concept of the New Storage Tank Looking North into the Site from across West Ox Road (Existing Elevated Tank can be seen behind the new tank)

Plan View

Project Schedule
Public Information Meeting 

April 2007

Design Complete

Spring 2008

Begin Project Construction

Fall 2008

Complete Project Construction

Spring 2010

Need More Information?

Mr. Steven Weisberger
Manager, Engineering

Construction
(703) 698-5600

Email: Engineering